Financial Target and Achievement of URP

Financial Progress (Fiscal Year – 2021-2022)

 

Sl. No
Implementing Agency
(Implementation Period)
Total Approved Cost
(In lac Tk.)
ADP Allocation
(2021-2022)
Cumulative total expenditure
from July 2015 to June 2017
and % of Exp/Approved Cost
Annual expenditure
from July 2017 to June 2018
and % of Exp/Approved Cost
Annual expenditure
from July 2018 to June 2019
and % of Exp/Approved Cost
Cumulative Total Expenditure & Progress
(From Jul-15 to Jun-2021)
Financial Expenditure & Progress for FY 21-22 (In lac Tk.)
Rolling total up to
Sep 2021 and
% of Exp/Approved Cost
Quarter-1 (From Jul-Sep, 2021) Quarter-2 (From Oct-Dec, 2021) Quarter-3 (From Jan-Mar, 2022) Quarter-4 (From Apr-Jun, 2022) Rolling Total of
FY21-22
and % of Exp/Alloc.
1
URP:  DDM
12,515.00
5,000.00
286.21 416.39 1,088.44 5,420.45 58.46 0.00 0.00 0.00 58.46 5,478.91
(01/07/2015 – 30/04/2022) 2.28% 3.32% 8.67% 43.31% 0% 0% 0% 0% 1.17% 43.78%
2
URP: DNCC
80,590.00
12,856.00
1,002.62 17,567.94 21,055.72 72.274.53 1,779.97 0.00 0.00 0.00 1,779.97 74,054.50
(01/07/2015-30/04/2022) 1.34% 23.55% 28.22% 89.68% 69.23% 0% 0% 0% 13.85% 91.89%
3
URP: RAJUK
53,665.00
15,600.00
244.29 1,306.87 5,141.00 25,619.83 3,592.24 0.00 0.00 0.00 3,592.24 29,212.07
(01/07/2015-30/04/2022) 0.57% 3.04% 11.96% 47.74% 102.64% 0% 0% 0% 23.03% 54.43%
4
URP: PCMU
4,530.00
700.00
60.25 320.85 648.15 2,293.74 127.12 0.00 0.00 0.00 127.12 2,420.86
(01/07/2015-30/04/2022) 0.75% 4.01% 8.10% 50.63% 72.64% 0% 0% 0% 18.16% 53.44%
Total
151,300.00
34,156.00
1,593.37 19,612.05 27,933.31 105,608.55 5,557.79 0.00 0.00 0.00 5,557.79 111,166.34
1.15% 14.20% 20.22% 69.80% 16.27% 0% 0% 0% 16.27% 73.47%

Disbursement

(In million US$)
IDA Disbursement Projections
for the FY 2020-2021 (USD m)
IDA Project Name
Financial Year
Total DPP Provision
Disbursement
(In million US$)
Percent of Disbursement Cumulative Disbursement
(In million US$)
Target Actual up to June’21
(including initial advance)
Target Actual
(up to June’21)
Target Actual
(up to June’21)
Bangladesh Urban Resilience Project
(DDM Part)
2020-2021 6.22 5.76 2.28 41% 16.3% 10.74 8.31
Bangladesh Urban Resilience Project
(DNCC Part)
2020-2021 37.94 37.21 31.58 39% 33.24% 83.86 70.48
Bangladesh Urban Resilience Project
(RAJUK Part)
2020-2021 19.81 18.12 14.12 31% 24% 40.88 34.24
Bangladesh Urban Resilience Project
(PCMU Part)
2020-2021 1.45 1.33 1.42 27% 28% 3.19 3.87